Construction of high-rise blocks of flats at High Barnet tube station moves a step closer after possible High Court challenge is abandoned

Unless there is a surprise last-minute legal objection Transport for London will shortly have full authority to proceed with its proposal to build five blocks of flats over the car park and container yard at High Barnet tube station.
Two community groups have finally admitted defeat in their long campaign against an application by TfL’s subsidiary Places for London to squeeze 328 new homes onto a narrow strip of land between the tube line and Barnet Hill.
After having already spent around £8,000 on legal advice, Barnet Residents Association and the Barnet Society have decided to abandon the possibility of making a joint application to the High Court to seek a judicial review.
They consider their withdrawal from any further protest action illustrates their inability to mount an effective challenge to the Mayor of London’s powers to rubber stamp a planning application which rode roughshod over the views of the local community.
After working together to try to thwart the plan, the two organisations have told their members they believe there is no “realistic” chance of halting construction.
An application to the High Court had to be made within a short sixty-day window.
After taking advice from a solicitor, leaders of the two groups sought the opinion of a King’s Counsel, but the view was that the chance of a successful challenge was “very low”.
A legal bill of around £8,000 is to be shared equally by the two organisations which say they have sufficient funds to meet the cost but now have low reserves and would appreciate any donations.

A mass demonstration last year opposite the tube station entrance demonstrated widespread opposition within the town to the loss of the station car park by the construction of high-rise blocks of flats on Barnet Hill which would cause “irreparable damage to an historic skyline”.
When Barnet Council refused permission for the five blocks of flats – one of which would be eleven storeys high – the application was called in the Mayor of London.
After a hearing in City Hall where community leaders gave evidence, Jules Pipe, Deputy Mayor for Planning and Regeneration, dismissed their objections and gave his approval in May.
For reasons yet to be explained it took three months longer than expected for a section 106 agreement to be issued between the developer and planning authority to control the development of the site.
Once the agreement was issued the society and residents’ association took legal advice on whether to seek a judicial review.
Going to the High Court could have cost up to £40,000 and would have required a massive fund-raising campaign, which the two organisations were prepared to launch if there was a reasonable chance of success.
“Unfortunately, the advice indicated that the chance of a successful challenge is very low,” they said a joint statement.
“The KC’s advice largely discounted the two issues we thought were the strongest – bias by the Deputy Mayor and the excessive height of the development.
“The failure of Barnet Council to insist on an Environmental Impact Assessment at the outset of the project offered a better possibility of success, but even then, only 50-50.
“We concluded that this alone was not sufficient to warrant continuing the challenge.
“We have therefore come to the conclusion that we should now put an end to the action. No doubt you will share our disappointment, but we have to be realistic.”

For the wider community there is a deep-seated sense of frustration, even betrayal, over the ability of the Mayor of London to ignore locally agreed policies such as the stipulation in the Barnet Local Plan that blocks of flats should be limited to seven storeys on sites in locations such as High Barnet.
Three of the five blocks will be higher than seven storeys, with tallest being eleven storeys.

In rejecting the criticism of the excessive height of the five blocks, a planning officer for the Greater London authority insisted that their height and massing responded well to the immediate area and would make “a positive contribution to the local townscape”.
A cause of even greater anger among residents was the Deputy Mayor’s dismissal of objections over the loss of 160 spaces in the station car park and the provision of only eight places for Blue Bag holders and only nine drop off short-stay spaces.
Mr Pipe rejected the protests on the grounds that encouraging tube passengers to walk to the station or take a bus would encourage “more sustainable means of travel and improve air quality”.
At the City Hall hearing earlier this year developers Barratt Homes of Places for London said they hoped to start construction by February 2027 with the first affordable homes becoming available in February 2029 and the whole scheme completed by April 2030.
A significant benefit of the scheme was that it would provide 100 affordable new homes at low-cost rent or shared ownership and there were “no material considerations of sufficient weight to justify refusal”.